When the new Kaya Grandi is finished, its center will sit higher than its edges. Engineers call this a roof profile. Rain that lands on the crown runs sideways to the curbs. There it meets at least ten new street drains, which feed a stormwater main that has been enlarged to 60 centimeters across, according to the Public Entity of Bonaire's October 30 progress update.
That buried design explains the barriers, the walking routes and the January dates downtown this December. The current work on Kaya Grandi is a drainage job first and a paving job second. The water decides the order of the work, and the order decides how downtown Kralendijk gets around until early 2027.
The rain that set the schedule
The third phase of the Kaya Grandi redesign was supposed to start years ago. In a July 9 interview with Bonaire.nu, Ligwino (Gino) Leito, director of Ruimte & Ontwikkeling at the Public Entity of Bonaire, said the designs had to be revised because drainage proved more complex than expected. He explained the priority this way, in Bonaire.nu's Dutch, translated here:
"We wanted to properly solve the drainage problem first before continuing with the reconstruction of the roads."
The same Bonaire.nu article pointed to the heavy rain of June 24, 2026, when parts of Kralendijk flooded again. Roads turned into temporary rivers, parking lots went under water and traffic came to a standstill. Leito described a system that will pass rainwater through several filter stages before it reaches the sea.
The rain has continued since then. The November 11 to 25 issue of The Bonaire Reporter ran a photo of Kaya L.D. Gerharts flooding after November's heavy rain, with crews in the middle of the upgrade meant to stop it. This is the reason the pipe goes in first. A new surface over the old drainage would flood the same way.
How the main street got to its third dig
Kaya Grandi has been worked on in stages since 2022. The phase numbers have been reused over the years, so a dated sequence is the clearest way to follow it.
| When | What happened on or near Kaya Grandi |
|---|---|
| September 19, 2022 | The earlier renovation began, with a first phase targeted before Christmas |
| Week of December 21, 2022 | Kaya Grandi reopened to all traffic after most of the shopping street was paved and the underground utilities were renewed. Finishing work resumed in the new year |
| August 7, 2023 | Kaya Isla Ariba closed fully between the Seaside Promenade and Kaya Grandi for the next stage |
| June 24, 2026 | Heavy rain flooded parts of central Kralendijk |
| August 14, 2026 | Information session with residents and business owners in the project area |
| Week of August 21, 2026 | Current reconstruction began, with a total expected duration of about seven months |
| Before end of 2026 | Target to finish the segment from Kaya Isla Ariba to Kaya L.D. Gerharts |
| January 2027 | Kaya Kòrsou and the final Kaya Grandi stretch to Kaya Boneiru are planned |
The 2022 design set the look of the street, with pavers in place of asphalt, tiled sidewalks, benches, more trees and streetlights. The 2026 phase brings back greenery, street lighting and benches, and adds better access for pedestrians and people with limited mobility. Bonaire.nu reported that the work started at the drainage across from the building where the Bestuurscollege works, then moved along Kaya Grandi toward the bend at MCB, with surrounding streets such as Kaya Prinses Marie included.
Why pedestrians get the street back before cars
The order of reopening follows from the drainage-first logic. The BES Reporter update of November 2 says the stretch from Kaya Isla Ariba to the Kaya L.D. Gerharts intersection is aimed for completion before the end of 2026. Once it is finished, that section opens to pedestrians. Cars come back only when the relevant work is complete and it is safe to reopen.
The next stretch toward Kaya Boneiru and the work on Kaya Kòrsou are planned for January 2027. So the finished section will likely carry foot traffic for a while before the whole route is ready for vehicles. Bonaire.nu's July report put completion of the full phase in the first months of 2027, and estimated about eight months for the Kaya Prinses Marie work.
The Public Entity of Bonaire has committed to these points for the length of the project:
- Every building in the project area stays reachable on foot.
- Pedestrians get safe, clearly marked walking routes.
- Emergency services keep access to the area.
- Temporary closures or diversions are announced in advance.
Leito summed up the hardest part of the job in the July Bonaire.nu interview: "The biggest challenge is keeping the area accessible while we work."
Where to leave the car
The practical answer for December is to park at the edge of the center and walk in. In a July 10 Bonaire.nu interview, Leito said the former Brionkazerne grounds had been leveled and marked as extra parking. He also said the parking on Kaya Prinses Marie is being reorganized and may gain one or more spaces.
He described a longer plan as well. Through the multi-year budget running to 2032, the island intends to pave many of its unpaved roads so drivers have more ways between points and fewer trips are funneled through the center.
A walking errand through the works area
With the car parked, the rebuilt streets are also where downtown eats, shops and buys ice cream. These are some of the names along the project streets, grouped by street:
- Kaya Grandi. Cuba Compagnie is at Kaya Grandi 1, beside Wilhelmina Park, with street-side and indoor tables. Bubbles is at 7-3 Kaya Grandi and serves lunch and dinner. Boudoir is at Kaya Grandi 26 F-G, and Donna & Giorgio Trattoria is at Kaya Grandi 52, where takeout is offered.
- Kaya L.D. Gerharts. Deli Delicious is at number 10 and Lilly's Ice Cream Shop is at number 5. This intersection marks the end of the current segment.
- Kaya Isla Riba. Playa Krioyo Restaurant is at Kaya Isla Riba 1, at the opposite end of the current segment.
- Kaya Kòrsou. Diver's Diner is at Kaya Kòrsou 1, on the street scheduled for work in January 2027.
Before heading out, it helps to check each place's own hours for the holiday weeks. The government's commitment to foot access applies to every building on these streets.
Sunday, November 22, at the Noord Pier
The busiest afternoon downtown in the coming days lands right after this post goes live. Bonaire.nu reports that Sinterklaas arrives by boat at the Noord Pier in central Kralendijk at 4:30 p.m. on Sunday, November 22. Activities for children and families start at 3:30 p.m. on Wilhelminaplein. The organizer, Alegria Tur Dia, chose the theme "Magia di Amistad," the magic of friendship, and promises music, dance and gifts.
Wilhelminaplein sits beside Cuba Compagnie's corner of Kaya Grandi. That makes the parking-at-the-edge approach worth using that afternoon. According to the same report, the arrival also opens the Sinterklaas season, and in the following weeks Pieten appear on the street almost daily across most of the island.
The other waterfront project due by year's end
Down on the waterfront, the fishermen's pier at Playa Pabou is also targeted for the end of 2026. BES Reporter wrote on November 6 that the renovation needed more time because the pile tops were in worse condition than expected and delivery of special materials was delayed. The plan calls for new sea-resistant wooden decking, and a use and management plan is being drawn up with special consideration for fishermen.
Both projects work the same edge of town, where the sea meets the street. On Kaya Grandi, the new drains will start proving themselves with the next heavy rain after the pedestrian section opens, when the water should run off the crown into the curbs.
Real estate in Kralendijk's center is priced partly on details like this one: which streets drain well and how close a front door is to the rebuilt core. For a closer look at how the downtown works affect a home or holding on Bonaire, the team at Bold Real Estate Aruba is glad to talk it through. Request a Private Consultation.